MBS INTERNATIONAL AIRPORT COMMISSION
February 9, 2009
MINUTES
A special meeting was held in the Airport Administration Building Conference Room, 8500 Garfield Road, Suite 104, Freeland, Michigan 48623. Chairman Kenneth Distler called the meeting to order at 5:13 p.m. Roll was called by Debbie Meisel.
Present Absent &
Excused Staff Other
Joyce
J. Seals
Chairman Distler introduced Christine Hartges who is the Acting Manager at the control tower.
PUBLIC COMMENT: None
PHASE
II TERMINAL CONSTRUCTION BIDS (AIP PROJECT #3909): Mr. Nagel stated that AIP Project #3909 includes several pieces of
work related to Phase II of the Terminal Construction Project. The following items are included in this
project:
-
Old
pavement removal
-
Construction
of a temporary construction access road
-
Minimal
tree removal
-
Structure
demolition
-
Construction
of a temporary fence around the site.
RS&H
has designed this project under the terminal design contract. Bids were received for this work on February
6, 2009 through the State bid letting process.
There were 19 total bidders with a low bid from Bierlein of $415,107.25,
which was 21% under the estimate of $523,060.
Based on a
review of all information submitted, it is the recommendation of RS&H to
award the contract to Bierlein Companies in the amount of $415,107.25. The State did not see any defects in the
bid. Mr. Gwizdala made a motion to approve
the bid of Bierlein Companies for the amount of $415,107.25 and authorize the
Chairman to sign all related documents for this contract. Mr. Earley seconded the motion. After discussion regarding the various items
in the project the motion passed unanimously.
PHASE
II TERMINAL CONSTRUCTION ADMINISTRATION (AIP PROJECT #3909): Mr.
Nagel stated that RS&H will be providing Construction Administration for
Phase II of the Terminal Construction process.
This service is not included in their ongoing terminal design
contract. Therefore, this service must
have a stand-alone contract amendment.
RS&H
has drafted a Construction Administration Contract in the amount of $41,000 to
provide these services. Mr. Nagel stated
that he received an email this week from the State Project Manager stating that
the contract had been reviewed and approved for that amount. Mr. Gwizdala made a motion to approve the
contract with RS&H to provide Construction Administration services for the
Terminal Construction Phase II Project and authorize the Chairman to sign all
related documents. Ms. Seals seconded
and the motion passed unanimously.
FAA
RCAG REIMBURSABLE AGREEMENT (AIP PROJECT #3909): Mr.
Nagel stated that the RCAG is the antenna complex that needs to be relocated
along with the ASOS which is a weather piece of equipment. Both need to be relocated in the terminal project. The process to move the FAA-owned RCAG and
ASOS equipment is dependent on obtaining Reimbursable Agreements from the
FAA. The first agreement, which the
Commission approved in December, 2007, in the amount of $44,250, covered the
preliminary engineering, site evaluation and planning. The equipment needs to be moved as soon as
possible so the grading can be completed.
The next
step in the process is to obtain an agreement with the FAA which covers the
next phase of the project. This work
includes:
-
Design
support
-
Construction
inspection
-
Establishment
of communication circuits
-
Equipment
installation.
The
estimated cost for the FAA agreement is $617,063.21 based on information
provided by the FAA. As with all FAA
Reimbursable Agreements, the sponsor (MBS) must make full payment in
advance. The airport will be reimbursed
95% through AIP Grant #3909 and reimbursed 2.5% through the State. The airport final cost will be 2.5% of the
project. It is important to note that
final FAA cost will vary depending on actual number of hours needed to complete
the scope of work.
The
movement of these facilities has been included in our ongoing Five-Year
Plan. The total estimated cost has been
between $1 million and $1.5 million.
RS&H will develop the plans in conjunction with the FAA and hopes to
bid the project yet this year.
This
agreement is needed to keep this piece of the terminal project moving forward. Mr. Gwizdala made a motion to approve the FAA
Reimbursable Agreement subject to final approval in the amount of $617,063.21,
authorize the Chairman to sign, and also authorize payment of the agreement for
submission into Grant #3909. Ms. Seals
seconded the motion. The new location of
the RCAG and ASOS was shown. There being
no further discussion the motion passed unanimously.
AIRFIELD
PAINT MARKING BIDS: Mr. Nagel stated that the runway paint
marking was originally placed in 2009 AIP Grant #4009. He was notified by the FAA just this week
that the painting is not eligible for FAA funding at this time. However, he is working with FAA in an attempt
to get the painting funded with AIP dollars when the 2009 “Part B” AIP program
is released scheduled for the spring.
This will take coordination between MBS, the FAA District Office in
Detroit and the FAA Certification/Safety Office in Chicago.
Working with
Peckham Engineering and the FAA the consensus was to receive bids as scheduled
on Friday, February 6, 2009. The
following bids were received:
PK
Contracting $78,803.78
Kenmark $79,398.14
Both bids
were under the engineer’s estimate of $93,000.
A recommendation was received from Bob Peckham to accept the bid of PK
Contracting for $78,803.78. This
recommendation is contingent on MBS receiving federal AIP funding for this
project. Mr. Gwizdala made a motion to approve the bid of PK
Contracting in the amount of $78,803.78 for the Runway Paint Marking contingent on
receiving FAA AIP funding for the project and also authorize the Chairman to
execute all related documents. Ms. Seals
seconded and the motion passed unanimously.
AIRFIELD PAINT MARKING CONSTRUCTION
SUPERVISION: Mr. Nagel stated that a contract must
be approved with Peckham Engineering to provide Construction Supervision during
the Airfield Paint Marking Project.
Bob Peckham
has drafted a contract to provide this service in the amount of $8,803.00. This contract is subject to review and
approval of our State Project Manager.
This contract should also be approved subject to MBS receiving an AIP
grant for painting. Mr. Gwizdala made a
motion to approve the contract
with Peckham Engineering to provide Construction Supervision for the Airfield
Paint Marking Project contingent on State approval and contingent on receiving
an AIP grant and authorize the Chairman to sign all related documents. Ms. Seals seconded and the motion passed
unanimously.
OLD BUSINESS: None
NEW BUSINESS: None
ADMINISTRATIVE MATTERS: Next regular meeting is scheduled for February 19, 2009.
Chairman Distler thanked everyone for making a special effort to attend this meeting.
ADJOURNMENT: There being no further business, Mr. Gwizdala made a motion to adjourn. Ms. Seals seconded and the Board unanimously passed the motion. The meeting adjourned at 5:32 p.m.
Eugene F. Gwizdala, Secretary