Scroll down the page to view information about City of Midland construction projects, or click on the purple links below.

Continuing Construction

Upcoming Construction

2008-2009 Construction Projects List

City Hall News – Sign Up For Construction Updates

 

TOP OF PAGE

 

Continuing Construction

W. Main Street Water Main

·         Final clean up in progress, road open to traffic

·         Lane restrictions

·         Estimated completion July 25

·         Map of Detour Routes/Project Area 

 

M-20/Jerome Street Bridge Repairs

·         MDOT Project

·         Lane closures

·         Estimated completion mid-August

 

E. Sugnet

·         Washington to Swede

·         Water main replacement, street reconstruction

·         Road closed to through traffic

·         Detour posted

·         Estimated completion August 30

·         Map of Project Area

 

Eastlawn

·         Jefferson to Saginaw

·         Street Reconstruction

·         Detour posted

·         Estimated completion mid-August

·         Map of Detour Routes/Project Area

 

 

Upcoming Construction

 

Surface Treatment Program

·         Chip seal application complete

·         Slurry seal and microsurfacing to start August 4

·         Map of Affected Areas

 

W. Sugnet Reconstruction

·         Eastman to Saginaw

·         Street reconstruction

·         Estimated start date mid-August

·         Map of Affected Areas

 

Baldwin Street

·         Street reconstruction

·         Storm sewer repairs

·         Estimated start date July 28

 

Valorie Lane

·         Sturgeon to St. Mary’s

·         Street reconstruction

·         Estimated start date early August

 

Dartmoor Place

·         Street reconstruction

·         Estimated start date mid-August

 

S. Saginaw R.R. Crossing

·         S. Saginaw south of Mark Putnam

·         Street paving

·         Saginaw Road reduced to one lane in each direction

·         Estimated start date July 28

 

TOP OF PAGE

 

2008 Construction Projects List

Project

Project Limits

Project Description

Est. Start Date

Est. Project Completion

E. Sugnet

Washington to Swede

Water Main Replacement from St. Andrews to Swede, Street Reconstruction, Selective Curb & Gutter Replacement

In Progress

 

 

August 30

Eastlawn Drive

Jefferson to Washington

Street Reconstruction, Selective Curb & Gutter Replacement

In Progress

Mid-August

Baldwin Street

Lancaster to Sugnet

Storm Sewer/Street Reconstruction

July 21

September

Valorie Lane

Sturgeon to St. Marys

Street Reconstruction, Selective Curb & Gutter Replacement

Early August

to be determined

Dartmoor Place

Nelson to End of Court

Street Reconstruction, Selective Curb & Gutter Replacement

Mid-August

to be determined

W. Sugnet Road

Eastman to Saginaw

Street Reconstruction

Mid-August

September

Rockwell Drive

Bay City Road to Fisher

Street Paving

August

October

Saginaw Road

Circle to Patrick

Rut Filling & Resurfacing

September

October

 

 

TOP OF PAGE

 

2008-2009 Construction Projects Map

Click here to download a map, in PDF format, of the projects that City Council has approved for 2008-09.