CITY OF MIDLAND
BID NO. 3244  
SAND & BLACK DIRT  
March 16, 2010  
 
                 
    MIDLAND SAND CO PATS GRADALL SOVA ECAVATING ANTHONY GUSHOW BILLY'S CONTRACTING  
      Midland Midland   Mildnad Auburn      
      UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
ITEM QTY DESCRIPTION COST COST COST COST COST COST COST COST COST COST
                           
A 3500 Cubic yards of Class II sand delivered to DPS 5.56 19,460.00 4.39 15,365.00 4.40 15,400.00 4.49 15,715.00   6.00 27,300.00
    per City specs                      
                           
                           
B 800 Cubic yards of black dirt delivered to DPS 12.00 9,600.00 7.49 5,992.00 10.00 8,000.00 8.15 6,520.00   12.63 14,145.00
    per City specs                    
                       
                           
    TOTAL BID:     29,060.00   21,357.00   23,400.00   22,235.00     41,445.00