CITY OF MIDLAND
BID NO. 3223
GAS COLLECTION SYSTEM
NOVEMBER 13, 2009
                 
GCCS - Davis Bacon & ARRA Requirements
Catskill Remedial Contracting Services Inc Miller Bothers Construction, Inc. SCS Field Services Anglin Civil Constructors, Ltd. Shaw Environmental & Infrastructure, Inc.
Bid Item Bid Item Description Unit Quantitiy     Unit Price Extended Price Unit Price Extended Price Unit Price Extended Price Unit Price Extended Price Unit Price Extended Price
                   
1 Mobilization / Demobilization LS 1   62,089.89 62,089.89 100,000.00 ######## 57,072.00 57,072.00 25,000.00 25,000.00 58,400.00 58,400.00
2 Temporary Controls LS 1   14,707.56 14,707.56 100,000.00 ######## 43,600.00 43,600.00 20,000.00 20,000.00 10,000.00 10,000.00
3 Gas Well Installation                        
3.1 Completed Well Installation LF 1095   91.48 100,170.60 65.00 71,175.00 98.00 107,310.00 110.00 120,450.00 96.00 105,120.00
3.2 Drilled and Abandoned - Refusal LF 100   52.29 5,229.00 35.00 3,500.00 70.00 7,000.00 200.00 20,000.00 55.00 5,500.00
3.3 2” Wellhead Assembly (CES Landtec Accu-Flo or Equivalent) EA 42   569.15 23,904.30 890.00 37,380.00 910.00 38,220.00 850.00 35,700.00 1,000.00 42,000.00
3.4 Remote Wellhead Assembly EA 23   1,110.46 25,540.58 250.00 5,750.00 630.00 14,490.00 1,000.00 23,000.00 750.00 17,250.00
4 Header Piping and Laterals                        
4.1 20-inch SDR-17 HDPE Pipe LF 150   55.81 8,371.50 79.00 11,850.00 120.00 18,000.00 48.00 7,200.00 100.00 15,000.00
4.2 18-inch SDR-17 HDPE Pipe LF 1495   63.09 94,319.55 40.00 59,800.00 62.00 92,690.00 40.00 59,800.00 43.00 64,285.00
4.3 16-inch SDR-17 HDPE Pipe LF 0     0.00   0.00   0.00   0.00   0.00
4.4 8-inch SDR-17 HDPE Pipe LF 7335   19.14 140,391.90 29.00 ######## 35.00 256,725.00 19.25 141,198.75 39.00 286,065.00
4.5 6-inch SDR-17 HDPE Pipe LF 480   20.94 10,051.20 18.00 8,640.00 32.00 15,360.00 22.00 10,560.00 20.00 9,600.00
4.7 Gas Extraction Manifold LS 1   867.15 867.15 1,200.00 1,200.00 980.00 980.00 1,500.00 1,500.00 1,200.00 1,200.00
5 LFG Horizontal Collection Trench                      
5.1 4-inch SDR-17 HDPE Pipe (Solid) LF 4300   14.87 63,941.00 13.00 55,900.00 28.00 120,400.00 17.50 75,250.00 21.00 90,300.00
5.2 4-inch SDR-17 HDPE Pipe (Perf) LF 2740   45.76 125,382.40 33.00 90,420.00 91.00 249,340.00 22.00 60,280.00 61.00 167,140.00
6 24-inch Culvert LF 20   20.52 410.40 40.00 800.00 130.00 2,600.00 52.00 1,040.00 45.00 900.00
7 Access Risers                      
7.1 18” Access Riser EA 3   3,282.22 9,846.66 3,000.00 9,000.00 2,700.00 8,100.00 4,342.00 13,026.00 250.00 750.00
7.2 8” Access Riser EA 7   1,592.79 11,149.53 1,600.00 11,200.00 1,700.00 11,900.00 1,320.00 9,240.00 110.00 770.00
7.3 4” Access Riser EA 0     0.00   0.00 1,200.00 0.00   0.00 110.00 0.00
8 Valves                        
8.1 18-inch Valve EA 1   15,941.00 15,941.00 15,000.00 15,000.00 11,100.00 11,100.00 16,000.00 16,000.00 15,000.00 15,000.00
8.2 8-inch Valve EA 6   2,617.63 15,705.78 3,000.00 18,000.00 2,600.00 15,600.00 4,400.00 26,400.00 2,800.00 16,800.00
8.3 4-inch Valve EA 7   1,747.10 12,229.70 1,800.00 12,600.00 2,050.00 14,350.00 3,200.00 22,400.00 1,700.00 11,900.00
9 Termination Points                        
9.1 18-inch Blind Flange EA 2   1,751.78 3,503.56 1,150.00 2,300.00 1,250.00 2,500.00 1,300.00 2,600.00 1,600.00 3,200.00
9.2 16-inch Blind Flange EA 0     0.00   0.00   0.00   0.00   0.00
10 Condensate Drip Leg EA 2   5,819.25 11,638.50 4,950.00 9,900.00 14,600.00 29,200.00 6,500.00 13,000.00 5,300.00 10,600.00
11 18-inch Condensate Straw Drain & 48-inch Knock-out EA 3   15,771.72 47,315.16 10,500.00 31,500.00 28,200.00 84,600.00 15,000.00 45,000.00 20,000.00 60,000.00
12 36-inch Condensate Knockout & 48-inch Lift Station System LS 1   38,056.66 38,056.66 38,000.00 38,000.00 58,000.00 58,000.00 33,000.00 33,000.00 65,000.00 65,000.00
13 Trenched Road Crossing LF 1   1,370.80 1,370.80 40.00 40.00 90.00 90.00 5,500.00 5,500.00 8,000.00 8,000.00
14 Flare System LS 1   195,563.20 195,563.20 206,000.00 ######## 262,000.00 262,000.00 ######## 213,500.00 ######## 291,780.00
15 Passive Flare Abandonment EA 2   724.15 1,448.30 650.00 1,300.00 2,700.00 5,400.00 2,000.00 4,000.00 2,500.00 5,000.00
                     
16 2-inch SDR-9 Air Supply Pipe LF 12,055   1.44 17,359.20 1.60 19,288.00 3.20 38,576.00 6.00 72,330.00 2.00 24,110.00
17 2-inch SDR-11 Leachate Pipe LF 8163   1.94 15,836.22 1.00 8,163.00 2.00 16,326.00 7.00 57,141.00 2.00 16,326.00
18 3-inch SDR-11 Leachate Pipe LF 3730   1.45 5,408.50 1.00 3,730.00 2.70 10,071.00 10.00 37,300.00 3.00 11,190.00
19 2”/4” Dual Contained Forcemain LF 270   3.83 1,034.10 10.00 2,700.00 32.00 8,640.00 18.00 4,860.00 11.00 2,970.00
20 3”/6” Dual Contained Forcemain LF 420   6.41 2,692.20 10.00 4,200.00 35.00 14,700.00 24.00 10,080.00 30.00 12,600.00
21 2-inch Ball Valve EA 18   447.43 8,053.74 450.00 8,100.00 900.00 16,200.00 1,778.78 32,018.04 950.00 17,100.00
22 3-inch Ball Valve EA 4   679.50 2,718.00 450.00 1,800.00 700.00 2,800.00 3,200.00 12,800.00 1,200.00 4,800.00
23 Cells 1- 8 VDW Well Upgrade EA 12   6,115.09 73,381.08 7,300.00 87,600.00 8,800.00 105,600.00 1,500.00 18,000.00 5,750.00 69,000.00
24 Electric Conduit LF 1450   7.06 10,237.00 22.50 32,625.00 18.00 26,100.00 18.00 26,100.00 30.00 43,500.00
25 Cells 1- 8 VW Well Upgrade EA 15   5,301.09 79,516.35 5,500.00 82,500.00 6,460.00 96,900.00 1,000.00 15,000.00 5,750.00 86,250.00
26 Cells 9-13 VW Well Abandon EA 19   200.41 3,807.79 930.00 17,670.00 1,950.00 37,050.00 800.00 15,200.00 600.00 11,400.00
27 Condensate Drip Leg w/ pump EA 5   9,394.46 46,972.30 10,500.00 52,500.00 19,800.00 99,000.00 13,000.00 65,000.00 10,500.00 52,500.00
                     
28 Seed and Mulch LS 1   22,524.88 22,524.88 15,500.00 15,500.00 42,200.00 42,200.00 15,000.00 15,000.00 23,000.00 23,000.00
29 Manhole repairs for Cells 1-13 EA 7   2,232.16 15,625.12 1,950.00 13,650.00 6,100.00 42,700.00 2,500.00 17,500.00 2,500.00 17,500.00
  1,344,312.36   ########   2,083,490.00   1,402,973.79   1,753,806.00