Building Department
Contact the Building Department Phone: 989-837-3383 Email: jwegner@midland-mi.org
Permit Expiration Dates
Projects must be completed before
the permit(s) issued for them expire.
The following permits are good for 180 days from the date of issuance
or from the last inspection:
-
building
-
electrical
-
plumbing
-
mechanical
-
fence
-
mobile home
-
grading
-
zoning compliance
Signs must be installed within 60 days from the date of
issuance of the permit.
Soil erosion and sedimentation control permits are good for one year.
Time Limitation of Application
An application for a permit for any proposed work will be
thought to have been
abandoned 180 days after the date of filing, unless the application has been
pursued in good faith or a permit has been insured; except that the building
official is authorized to grant one or more extensions of time for additional
periods not exceeding 90 days each. The extension must be requested in
writing, and justifiable cause demonstrated.
|